Winter construction measures for metal workshop building

Time:[2021-11-24]  Hits:2767

a. The winter construction of steel structure production and installation shall be carried out strictly in accordance with the relevant steel structure winter construction regulations.

b. When steel components are installed at positive temperature and at negative temperature, the shrinkage of components should be considered according to the difference in ambient temperature, and technical measures to adjust deviation should be taken during construction.

c. Welders who participate in the construction of negative temperature steel structures should undergo negative temperature welding process training, pass the examination, and obtain corresponding certificates.

d. The steel and related connecting materials used under negative temperature must be accompanied by a quality certificate, and the performance meets the requirements of the design and product standards.

e. The welding rod used under negative temperature shall not be exposed for more than 2 hours, and it shall be re-baked after more than 2 hours, and the number of baking of the welding rod shall not exceed 3 times.


f. Bake the flux according to the regulations before use, so that the water content does not exceed 0.1%.

g. High-strength bolts used under negative temperature must have a product certificate, and the torque coefficient and axial force must be re-inspected under negative temperature.

h. The paint used for steel structure under negative temperature shall not use water-based paint.

i. When the component is blanked, a shrinkage margin should be reserved, and the welding shrinkage and compression deformation should be coordinated with the shrinkage deformation of the steel under negative temperature.

j. When assembling the components, expand the assembly from the inside to the outside according to the order stipulated by the process, and do a test during the assembly of the negative temperature to determine the shrinkage value of the weld that needs to be reserved.

k. When assembling components, remove rust, burrs, soil, oil, ice and snow and other debris remaining in the joint 50mm, and keep the joints dry and free of residual moisture.

l. Multi-layer welding should be used when welding steel plates above 9mm under negative temperature. The welds should be welded layer by layer from bottom to top. Each weld is completed at a time. If the welding is interrupted, the welding defects should be removed before welding again. It is strictly forbidden to start the arc on the welding base metal.

m. When the steel structure is installed on site, in case of snow or wind speed above 6m/s, set up a protective shed.

n. The unqualified welds shall be removed and re-welded, and the welding shall be carried out in accordance with the provisions of the welding process of the steel structure under negative temperature.

o. When the ambient temperature is lower than 0°C, perform the painting process test before applying the anti-corrosion coating. When painting, the rust, oil stains, burrs, etc. on the surface of the component must be cleaned up, and the surface must be kept dry. No painting work is allowed in snowy weather or when there is thin ice on the components.

p. Take anti-skid measures when transporting and stacking steel structures in winter. The component stacking site is flat and solid without puddles, and the ground is free of icing. When the components of the same model are stacked, the components should be kept horizontal, and the shims should be placed on the same vertical line to prevent the components from slipping.

q. Before the steel structure is installed, its quality shall be re-inspected according to the requirements under negative temperature conditions, and the components that have been missed in the production and deformed during transportation and stacking shall be repaired and corrected on the ground.

r. When using steel cables to hoist steel components, anti-skid spacers should be added, the gusset plate that is hoisted at the same time as the components, and the fixtures required by the installer should be tied firmly with ropes.

s. According to the temperature conditions, the steel component installation sequence chart is compiled, and the installation shall be carried out in strict accordance with the specified sequence during construction.

t. Prepare the welding process for steel structure installation, and both ends of a component shall not be welded at the same time.

u. Before installation, remove ice, snow and dew on the surface of the components, but do not damage the coating.

v. Columns and main beams installed at negative temperature shall be corrected immediately, and the correct position shall be immediately fixed permanently. The components installed on the same day shall form a stable space system.

w. When installing high-strength bolt joints, there must be no snow or ice on the friction surface of the components, and no contact with dirt, oil and other stolen objects.

x.In addition to complying with the requirements of "Code for Construction and Acceptance of Steel Structure Engineering" (GB50250-95), the quality of steel structure installation under negative temperature should also be inspected and accepted according to design requirements.

Copyright:佛山市勝邦鋼結(jié)構(gòu)有限公司 Foshan Shengbang Steel Structure Co., Ltd. Record Number:粵ICP備13078463號
主站蜘蛛池模板: 楼宇门厂家-氟碳漆门-不锈钢大门-单元门-锌合金大门-永康市龙卫门业 | 西安泰富西玛电机有限公司总部-电机-高压电机-西玛电机-西安西玛电机-泰富西玛电机-西安电机厂-西玛电机销售 | 宁波明驰同步带有限公司| 箱包定制_广州箱包厂_双肩电脑背包_双肩旅行包_拉杆箱包_商务公文包_包包批发,深圳爱自由,礼品箱包定制,电话:400-0061-690 | 面粉加工设备-面粉加工机械-面粉机组-面粉磨粉机-面粉机成套设备-河南粮院机械制造有限公司 | 挖掘机|小型挖掘机|挖掘机抓木机|轮式挖掘机|宝鼎挖掘机-宝鼎液压机械公司厂家直销 | 拉力机|拉力试验机|拉力测试机厂家-苏州天氏库力精密仪器有限公司 | 指挥调度|调度系统|应急指挥调度|应急指挥|可视化调度|多媒体指挥调度|融合通信|综合调度|应急指挥系统|IP调度系统-北京瑞光极远数码科技有限公司 | 水处理设备_纯净水设备_软化水设备_反渗透水处理设备「陕西甘肃青海宁夏新疆」认准海川环保 | 智能门锁管理-公寓管理软件-智能水电表管理系统-深圳安安智能 | 耐磨颗粒胶_陶瓷颗粒胶_大小颗粒耐磨胶_耐磨防护胶-北京耐默 | 宿迁市华泰交通设施有限公司,上海第四代路名牌,天津仿罗马柱路名牌,标准路名牌,路名牌灯箱,公交站台,户外广告灯箱, 交通标志牌,社区阅报栏 | 郑州专利申请代理|商标注册|河南版权登记-郑州明华专利代理事务所 | 小字符喷码机,激光喷码机,喷码机厂家_山东闪创电子设备有限公司 小型生活污水处理设备_MBR膜生物反应器_口腔医院/脱脂污水处理设备_酸洗磷化/喷涂废水处理设备-上海台江环保 | 九江江菱电梯有限公司| 河南车用尿素设备_郑州车用尿素设备_河南江宇环保车用尿素液厂家 | 酸碱废气中和塔-酸雾废气吸收塔-酸雾废气处理塔|首页-广州市佰镀通风设备有限公司 | 酸碱废气中和塔-酸雾废气吸收塔-酸雾废气处理塔|首页-广州市佰镀通风设备有限公司 | 质保_天津光栅尺_机床光栅尺数显表-天津方韦仪器有限公司 | 河南豫冀锅炉容器制造有限公司| 郑州建网站,郑州做网站,郑州网站建设,郑州网站制作,郑州高端定制网站,郑州APP开发 | 耐磨锤头|合金锤头|高铬耐磨锤头|破碎机锤头|双金属双液复合锤头_巩义东辰实业 合金耐磨锤头铸造厂 | 文化艺术网-专注文化,服务艺术 温州网络公司_网站建设_网络营销策划_阿里淘宝店铺服务-温州聚欣网络科技有限公司 | 无尘投料站-真空上料机-旋振筛|超声波振动筛|摇摆筛|筛分机-新乡市欧霖佳机械有限公司 | 呼吸家官网|肺功能检测仪生产厂家|国产肺功能仪知名品牌|肺功能检测仪|肺功能测试仪|婴幼儿肺功能仪|弥散残气肺功能仪|肺功能测试系统|广州红象医疗科技有限公司|便携式肺功能仪|大肺功能仪|呼吸康复一体机|儿童肺功能仪|肺活量计|医用简易肺功能仪|呼吸康复系统|肺功能仪|弥散肺功能仪(大肺)|便携式肺功能检测仪|肺康复|呼吸肌力测定肺功能仪|肺功能测定仪|呼吸神经肌肉刺激仪|便携式肺功能 | 领先的木工机械生产厂家,原木加工流水线,立式带锯机,数控木工跑车-邢台亚士达机械制造有限公司 | 小型静音无油空压机价格-医用无油制氧空气压缩机-浙江盛源水润滑空压机制造有限公司 | 视频监控|安防监控|智能防火|智慧城市-浩海科技 | 网站建设-百度SEO关键词优化与企业全网营销推广服务-启源信息 | 氢能-燃料电池-电堆-中国氢能与燃料电池网企业最佳宣传推广平台 轻质隔墙板厂家-加气隔墙板_grc轻质隔墙板_空心实心复合隔墙板_水泥混凝土轻质隔墙板批发价格 | 新零售策划-全渠道策划-品牌营销全案策划-上海韬慧管理咨询有限公司 | 济南牛皮癣专科研究院_「济南市银屑病医院」_济南治牛皮癣医保医院_济南正规的银屑病医院 | 铝合金热处理设备_天然气铝棒加热炉_QPQ热处理设备-浙江长兴天源炉业科技有限公司 | 制冷机组|地源热泵|冷水机组|磁悬浮冷水机组-山东鹏鲲空调官网 | 山东发电机组生产厂家,特种火花塞生产厂家,高压线生产厂家,空气滤芯生产厂家,济南市博盛动力机械有限公司 | 汽车蓄电池配件_蓄电池维护保养产品_叉车电池配件研发生产厂家—联鸿能源 | 浙江创洁卫生消杀有限公司-浙江杀虫公司,温州消杀公司,温州灭鼠公司,灭蟑螂,灭蚊蝇,灭跳蚤,灭书虱,灭臭虫,灭螨虫,白蚁防治,房间消毒除味等专业服务 | 新能源洗扫车、新能源压缩垃圾车_新能源路面养护车_电动树叶收集车_电动扫地机_电动洗地机_高尔夫球车 | 合肥固化地坪-安徽耐磨地坪-合肥环氧地坪厂家-安徽玉平地坪工程有限公司 | 墙板_户外墙板_ASA共挤户外墙板-康亿家生态木业集团 | 生物除臭剂-养殖场垃圾除臭剂-垃圾填埋场除臭剂-成都微菌环境 |